Skip to content

All rule changes

Proposed Electric

Promoting a Competitive Market for Capacity Reassignments

Issued by Energy Department, Federal Energy Regulatory Commission

Published
Comment deadline
Effective
Not set

Summary from the Federal Register

Based on the Commission's experience to date and a two-year study, released April 15, 2010, the Federal Energy Regulatory Commission proposes in this Notice of Proposed Rulemaking to lift the price cap for all transmission customers reassigning transmission capacity beyond October 1, 2010. The reforms proposed in this order are intended to facilitate the development of a market for capacity reassignments as a competitive alternative to primary capacity.

Read the full document on federalregister.gov (opens in a new tab)

Docket

  • RM10-22-000

Informational, not legal advice; confirm with your primacy agency or counsel.

Source: Federal Register document 2010-10500. Checked against the Federal Register several times a day.