Effective Electric
Reform of Generator Interconnection Procedures and Agreements
Issued by Energy Department, Federal Energy Regulatory Commission
- Published
- Comment deadline
- Not set
- Effective
Summary from the Federal Register
In this final action, the Federal Energy Regulatory Commission (Commission) is amending the pro forma Large Generator Interconnection Procedures and the pro forma Large Generator Interconnection Agreement to improve certainty, promote more informed interconnection, and enhance interconnection processes. The reforms are intended to ensure that the generator interconnection process is just and reasonable and not unduly discriminatory or preferential.
Docket
- RM17-8-000
- Order No. 845
Informational, not legal advice; confirm with your primacy agency or counsel.
Source: Federal Register document 2018-08659. Checked against the Federal Register several times a day.