Effective Electric

Reform of Generator Interconnection Procedures and Agreements

Issued by Energy Department, Federal Energy Regulatory Commission

Published
Comment deadline
Not set
Effective

Summary from the Federal Register

In this final action, the Federal Energy Regulatory Commission (Commission) is amending the pro forma Large Generator Interconnection Procedures and the pro forma Large Generator Interconnection Agreement to improve certainty, promote more informed interconnection, and enhance interconnection processes. The reforms are intended to ensure that the generator interconnection process is just and reasonable and not unduly discriminatory or preferential.

Read the full document on federalregister.gov (opens in a new tab)

Docket

  • RM17-8-000
  • Order No. 845

Informational, not legal advice; confirm with your primacy agency or counsel.